The third operation of the capping of Baghjan oil well continued as the expert team has set up the Blow out Preventer (BOP) on Monday. The operation is going on successfully till the filing of this report.

The expert team also tried to install the BOP on August 10 but due to some technical error it was uninstalled.

The OIL and the expert team said that once the BOP would be installed successfully, the capping of the oil well would be successful.

The OIL officials said that all bolts have bee placed and Athey wagon removed from BoP stack. Things are progressing well so far.

The officials stated that the capping has been done and the killing operation will be undertaken in 2-3 hours, which might take 24-36 hours.

Operation underway to douse the flame

Travel & Tourism Sector Poised to Create 58.2 Million Jobs by 2033: NLB Services

Presiding Officer Suspended Over Negligence on Duty in Assam's Karimganj

Two Including Former Cop Dead in Fatal Road Accidents Across Assam

Assam: 2 Brothers Charred to Death as Fire Engulfs House in Goroimari

Horoscope Today, April 30: Check Tarot Readings For Your Zodiac